Awaab's Law requirements and deadlines
The complete breakdown
Understanding Exactly What You Need to Do, When You Need to Do It, and What Happens If You Don’t
Awaab’s Law came into force on 27 October 2025, changing how social landlords must respond to hazards in their homes. The first phase introduced legally enforceable timescales for responding to all emergency hazards and significant damp and mould hazards.
The word “requirements” might sound bureaucratic, but these aren’t simply administrative hurdles. They’re about making sure that when residents report potentially serious problems in their homes, those concerns are investigated and acted upon within clear timescales.
The Reality Check
Under the first phase of Awaab’s Law, social landlords must follow specific timescales when responding to potential emergency hazards and significant damp and mould hazards.
For significant damp and mould hazards, landlords must investigate within 10 working days.
Where there are reasonable grounds to believe a potential emergency hazard exists, landlords must investigate as soon as reasonably practicable and within 24 hours. If the investigation confirms an emergency hazard, the necessary safety work must also be completed within that 24-hour period.
Where the property cannot be made safe within the required timeframe, suitable alternative accommodation must be offered at the landlord’s expense.
That’s not just a change in process, it’s a fundamental change in the expectations placed on social landlords.
The Two-Track System That Changes Everything
Awaab’s Law creates two distinct pathways for dealing with reported hazards – Emergency or Significant – and is now person-centred, requiring landlords to consider the tenant’s health, vulnerabilities, and circumstances.
Getting this distinction right is absolutely crucial. Make the wrong call, and you could find yourself in breach of legal requirements within hours rather than days.
Emergency Hazards – 24 Hours to Investigate and Make Safe
What makes something an emergency?
An emergency hazard is one that poses an imminent and significant risk of harm to the health or safety of the resident.
When a problem is first reported, you may not have enough information to know whether it meets that threshold. Where there are reasonable grounds to believe a potential emergency hazard exists, it must be investigated as soon as reasonably practicable and within 24 hours of the landlord becoming aware of it.
Examples of reports that could require urgent investigation include:
- Extensive mould where there are concerns about an immediate risk to a resident’s health
- Severe damp or water ingress affecting the safety of the building
- Water ingress creating potentially dangerous electrical hazards
- Serious contamination or other conditions that may present an imminent and significant risk of harm
Whether a particular case is an emergency will depend on the circumstances, including the nature and severity of the hazard and the individual circumstances of the resident.
Your Emergency Obligations:
- Within 24 hours: Investigate where there are reasonable grounds to believe a potential emergency hazard exists
- If an emergency hazard is confirmed: Complete the necessary safety work as soon as reasonably practicable and within that same 24-hour period
- Written summary: Provide the resident with a written summary of the investigation findings within the applicable timeframe
- If the property cannot be made safe within the required timeframe: Offer suitable alternative accommodation at the landlord’s expense
Significant Hazards – 10 Working Days to Investigate
Under the first phase of Awaab’s Law, the significant hazard requirements apply to significant damp and mould hazards.
A significant hazard is one that poses a significant risk of harm to the health or safety of the resident but does not meet the threshold for an emergency hazard.
Typical Scenarios:
- Persistent condensation and mould growth requiring investigation
- Damp patches that are worsening but do not appear to present an imminent and significant risk
- Ventilation problems contributing to damp and mould
- Mould requiring professional investigation to establish its extent, cause and risk
Your Significant Hazard Obligations:
- Within 10 working days: Complete an investigation of the potential significant hazard
- Within 3 working days of the investigation concluding: Provide the resident with a written summary of the findings, unless the applicable exception applies
- Within 5 working days of the investigation concluding: Complete any relevant safety work required to make the home safe from the significant hazard
- Further preventative work: Begin the work, or take steps to begin it, within five working days of the investigation concluding
- Where preventative work cannot begin within five working days: The work must physically begin within 12 weeks
- Completion: Complete the work within a reasonable period
The Critical First Assessment: Getting It Right from Day One
The initial assessment is critical because the information available may determine whether the case needs to follow the emergency response route or the significant hazard process.
When a resident reports a potential hazard, the first priority is to gather enough information to understand the nature of the problem, the potential risk and whether there are reasonable grounds to believe an emergency hazard may exist.
Questions to ask during the initial assessment
What is the nature and severity of the problem?
Consider:
- What has the resident reported?
- Which areas of the home are affected?
- How extensive is the problem?
- Is the condition getting worse?
- Are there additional risks, such as water affecting electrical installations or concerns about structural safety?
Who is being exposed to the hazard?
The risk presented by a hazard can depend on the individual circumstances of the people living in the property.
Consider relevant information such as:
- the age of household members
- disabilities or health conditions where relevant to the hazard
- how frequently residents are exposed
- whether the affected area can reasonably be avoided
- whether essential rooms or facilities are affected
The purpose is not to make a medical diagnosis. It is to understand the risk that the reported condition may present to the people actually living in the home.
How immediate is the potential risk?
Consider:
- whether there are indications of an imminent and significant risk of harm
- whether the condition could deteriorate rapidly
- whether immediate action may be needed to prevent harm
- whether the property, or the affected part of it, can currently be occupied safely
What happens if you don’t have enough information?
Frontline staff may not always be able to determine immediately whether a reported problem meets the threshold for an emergency hazard.
Where the available information gives reasonable grounds to believe a potential emergency hazard may exist, the case should be escalated for appropriate investigation rather than delayed while staff try to reach a definitive technical diagnosis.
Clear escalation routes are therefore essential. Staff need to know who can assess the available evidence, what information that person needs and how the case should be progressed when the level of risk is uncertain.
The information gathered, decisions made and reasons for those decisions should be clearly recorded.ond within 24 hours unnecessarily than to take 10 days when you should have taken one.
Investigation Requirements That Actually Mean Something
Let’s talk about what “investigation” means under Awaab’s Law because the purpose is to establish whether a significant or emergency hazard exists and what action is required.
The Investigation Standard You’ll Need to Meet
Appropriate Expertise
The person carrying out the investigation should have the appropriate skills and competence for the nature of the potential hazard.
Depending on the circumstances, this could require knowledge of:
- Different types of damp and their potential causes
- Mould and the risks associated with it
- Building defects and building pathology
- Relevant health and safety risks
- How the resident’s individual circumstances may affect the level of risk
Where specialist expertise is required, providers should have appropriate arrangements for accessing it.
Thorough Assessment
The investigation should establish the nature and extent of the potential hazard and determine what action is required.
Depending on the case, this may include considering:
- The type and extent of the potential hazard
- The underlying cause rather than simply the visible symptoms
- The risk presented to the people living in the property
- Any safety work required
- Further work required to prevent the hazard from recurring
Proper Documentation
The investigation and its findings should be clearly recorded.
Good records can demonstrate what information was considered, what conclusions were reached and why particular actions were taken.
The Reality of Investigation Timescales
Ten working days can sound like plenty, until you consider everything that may need to happen within that period.
This could include:
- Arranging access with the resident
- Carrying out the investigation
- Obtaining any additional technical or specialist input required
- Reviewing the findings
- Determining what action is necessary
Providers therefore need processes that allow potential significant hazards to be investigated within the statutory timeframe, including arrangements for situations such as access difficulties or the need for further specialist input.
Written Reports: What Tenants Actually Need to Know
The written summary is an important part of the Awaab’s Law process. It gives residents a clear record of what the investigation found and what happens next.
What Your Written Summary Must Include
The written summary should set out:
- Whether the investigation identified a significant or emergency hazard and, if so, what the hazard is
- What action is required
- Target timescales for beginning and completing that action
- If no action is required under Awaab’s Law, confirmation of this and the reasons why
- Information explaining how the resident can contact the landlord
The summary should be clear and accessible to the resident.
The Three Working Day Rule
Following an investigation, the landlord must usually provide the resident with a written summary within three working days of the investigation concluding.
The three-working-day period is the deadline for the landlord to send or otherwise provide the summary, rather than for the resident to receive it where it is being sent by post.
There is an exception where all required work – both the work needed to make the home safe and any work needed to prevent the hazard recurring – has been completed within the three-working-day period. In those circumstances, a written summary is not required, although the resident must still be informed that the work has been completed.
If safety work has been completed but further work is still required to address the underlying problem, the written summary is still required.
Repair Timescales: When “As Soon As Possible” Becomes Legally Binding
Investigation is only the first stage. Where a significant hazard is identified, Awaab’s Law also sets timescales for the work needed to make the home safe and prevent the hazard from recurring.
Safety Work: Within 5 Working Days
Where an investigation identifies a significant hazard, any relevant safety work must be completed as soon as reasonably practicable and within five working days of the investigation concluding.
Safety work is the work needed to make the property safe from the hazard identified.
What that involves will depend on the circumstances. In some cases, the safety work may resolve the problem completely. In others, further work may still be required to address the underlying cause and prevent the hazard from recurring.
Further Preventative Work
Where additional work is required to prevent the hazard from recurring, the landlord must begin that work – or take steps to begin it – within five working days of the investigation concluding.
Taking steps to begin the work could include actions such as:
- Arranging appointments
- Securing an appropriate contractor
- Ordering necessary materials
- Arranging access
- Commissioning specialist work
This is an important distinction. The five-working-day requirement does not necessarily mean that physical work must have started on site within five working days.
The 12-Week Backstop
Where it isn’t reasonably practicable for the physical preventative work to begin within five working days, it must begin within 12 weeks of the investigation concluding.
The work must then be completed within a reasonable period.
The 12-week period shouldn’t be treated as the standard target. Providers are still expected to progress the work as soon as reasonably practicable.
Emergency Hazards Are Different
The five-working-day and 12-week timescales shouldn’t be confused with the requirements for emergency hazards.
Where there are reasonable grounds to believe a potential emergency hazard exists, the investigation must take place as soon as reasonably practicable and within 24 hours.
If that investigation confirms an emergency hazard, the relevant safety work must also be completed within that same 24-hour period.
If the home cannot be made safe within the required timeframe, suitable alternative accommodation must be offered at the landlord’s expense.
Which Hazards Are Covered by Awaab’s Law?
Awaab’s Law is being implemented in phases, with different hazards brought within the statutory requirements at each stage.
Phase 1: From 27 October 2025
The first phase of Awaab’s Law applies to:
- All emergency hazards – where a hazard presents an imminent and significant risk of harm to the health or safety of the resident
- Significant damp and mould hazards – where damp or mould presents a significant risk of harm but does not meet the threshold for an emergency hazard
Importantly, the emergency requirements aren’t limited to damp and mould. Any hazard that meets the definition of an emergency hazard can fall within the 24-hour requirements.
Phase 2: From 30 November 2026
Phase 2 extends the significant hazard requirements to additional hazards, including:
- Excess cold
- Excess heat
- Falls associated with baths and similar facilities
- Falls on level surfaces
- Falls associated with stairs and ramps
- Falls between levels
- Structural collapse and falling elements
- Fire
- Explosions
- Electrical hazards
- Domestic and personal hygiene and food safety hazards
This brings a much broader range of significant hazards within the Awaab’s Law investigation and response requirements.
Phase 3: Planned for 2027
The government plans to extend Awaab’s Law to the remaining hazards covered by the Housing Health and Safety Rating System in 2027, with the exception of overcrowding.
Taken together, the phased implementation means Awaab’s Law extends considerably beyond damp and mould, affecting how social landlords investigate and respond to hazards across their homes.
Record Keeping: Your Protection and Their Rights
Good record keeping is both your defence and your tenant’s evidence.
What Records You Need to Maintain
Initial Reports and Assessments
- Date, time, and method of report
- Tenant details and description
- Risk categorisation
- Decision rationale
- Immediate actions
Investigation Documentation
- Investigator qualifications
- Site reports, photos, and measurements
- Findings and analysis
- Risk assessments
- Recommended remedial actions
Communications and Actions
- All tenant correspondence
- Proof of written summaries
- Contractor schedules and updates
- Completion certificates
- Alternative accommodation records
Data Protection Considerations
Investigations may involve information about a resident’s health, which can constitute special category data under UK GDPR.
Key considerations include:
- Having an appropriate lawful basis for processing personal data
- Identifying an appropriate condition for processing special category data where required
- Being transparent with residents about how their information will be used
- Collecting only the information that is relevant and necessary
- Keeping personal information secure
- Applying appropriate retention periods
Record-keeping systems should allow providers to maintain a clear audit trail of reports, assessments, decisions, communications and actions taken throughout the case. Integrated IT systems should also enable cross-referencing with the Pre-Action Protocol for Housing Conditions Claims to show systematic compliance.
What Happens When Things Go Wrong
Awaab’s Law gives residents clear routes to challenge failures where landlords do not meet their obligations.
Housing Ombudsman
Residents can take unresolved complaints to the Housing Ombudsman after using their landlord’s complaints process, or where the landlord is not responding appropriately to a complaint.
The Ombudsman can consider whether the landlord:
- Recognised and responded appropriately to a potential hazard
- Complied with the relevant Awaab’s Law timescales
- Followed its own policies and procedures
- Communicated appropriately with the resident
- Kept adequate records
- Considered suitable alternative accommodation where required
Where things have gone wrong, the Ombudsman can make findings of maladministration and order remedies such as an apology, compensation, inspections, works or changes to policies and practices.
Court Action
Awaab’s Law implies terms into social housing tenancy agreements requiring landlords to comply with the prescribed requirements.
Where a landlord fails to comply, a resident can take legal action for breach of contract.
If the court finds the landlord in breach, it can order the landlord to:
- Carry out the required repairs
- Pay compensation to the resident
- Pay some or all of the resident’s legal costs
Awaab’s Law does not itself provide for fines to be imposed on landlords through this court process.
Regulator of Social Housing
The Regulator of Social Housing does not resolve individual Awaab’s Law complaints.
Its role is to regulate registered providers and assess whether they are delivering the outcomes required by the regulatory standards.
The Safety and Quality Standard requires registered providers to meet legal health and safety requirements, including Awaab’s Law.
Where failures indicate a wider or material failure to deliver the required outcomes, the Regulator has a range of regulatory and enforcement powers available.
How to Avoid Enforcement Action
Reducing the risk of non-compliance requires providers to make Awaab’s Law part of their day-to-day housing and repairs processes.
Key areas include:
- Clear policies and consistent application
- Appropriate training for relevant staff
- Reliable contractor and specialist arrangements
- Systems that support the required investigation, repair and communication timescales
- Clear escalation routes for potential emergency hazards
- Regular review of cases and performance to identify where processes need to improve
The Essentials You Need in Place
- Qualified investigators
- Emergency response contractors
- Rapid response repair teams
- Integrated IT systems
How PfH’s Frameworks Can Help
Meeting Awaab’s Law requirements may require access to a range of specialist services, from investigation and surveying through to damp and mould treatment, remedial works and wider compliance support.
PfH’s procurement solutions can help members access suppliers across services that may support different parts of their Awaab’s Law response.
Depending on your requirements, this could include:
- Investigation and surveying support
- Damp and mould treatment and remediation
- Specialist property compliance services
- Repairs and remedial works
- Additional contractor capacity where internal resources are under pressure
- Managed solutions where several services need to be coordinated
Using an established procurement route can help providers put appropriate contractual arrangements in place without starting a new procurement exercise every time additional capacity or specialist expertise is required.
However, providers should still make sure that the service commissioned meets their specific Awaab’s Law requirements, including relevant response times, geographic coverage, technical competence, reporting and capacity.
PfH can help members understand the procurement options available and identify an appropriate route for the services they require.
Damp and Mould Specialists Ready to Respond
Our framework includes contractors specialising in damp and mould investigation, treatment, and prevention – pre-vetted to meet 10-day investigation requirements.
Find damp and mould specialists here
Strengthening Your Awaab’s Law Response
Awaab’s Law requires more than a change to repairs timescales. Providers need the right processes, people, systems and supply chain in place to identify hazards, investigate them within the required timescales and complete the necessary work.
As the requirements extend across further hazards, providers should continue to review:
- Investigation and triage processes
- Emergency response arrangements
- Contractor and specialist capacity
- Staff training and escalation routes
- Record keeping and resident communication
- Performance against the statutory timescales
PfH can support members with procurement solutions across property compliance, investigation, damp and mould, repairs and other services that can form part of an effective Awaab’s Law response.
Speak to PfH about the procurement solutions available to support your Awaab’s Law requirements.
Awaab’s Law – Additional Resources:
- Awaab’s Law: Your Complete Guide to the New Social Housing Regulations
- Spotlight Report on Damp and Mould – Interview with Catherine Ryder, Director of Research and Policy, National Housing Federation, and Richard Blakeway, Housing Ombudsman
Delivered By
Bradley Hughes – PfH Category Manager for Materials
Ben How – Head of Retrofit and Sustainability, Frankham Group
Frankham Group are one of the top-ranked Damp and Mould surveyors on the PfH Compliance Solutions framework for social housing providers.

About Ben How
Ben How is a qualified surveyor and energy efficiency specialist with more than 15 years’ experience in the construction and housing sectors.
Currently Head of Retrofit and Sustainability at Frankham Group, Ben has also held senior roles as Director of Sustainability and Decarbonisation at Breyer Group and Energy & Innovation Commercial Manager at ENGIE.
His expertise spans retrofit delivery, carbon management, renewable technologies, modular and low-carbon housing, and sustainability strategy.
As a CoRE Retrofit Coordinator and certified Thermographer, Ben combines technical knowledge with commercial acumen, helping clients decarbonise housing stock and implement innovative energy solutions.
About Bradley Hughes
Bradley Hughes, MCIPS, is a seasoned procurement professional with over a decade of experience in public-sector frameworks and supply chain strategy.
As Category Manager for Materials at PfH, he has also managed categories across Fire Safety and Compliance services.
He holds Chartered Institute of Purchasing & Supply accreditation and has led operations that deliver value, efficiency, and compliance at scale.
Beyond his operational role, Bradley contributes thought leadership on sustainable procurement, best practice, and innovation in sourcing, helping clients achieve better outcomes through smarter procurement.